Following damp issues reported at Flats 20 & 23, Croft Surveyors were instructed to investigate the problem. It was found that leaks were likely to be occurring in the single ply membranes lining the parapet box gutters with the need to re-waterproof and replace decayed timber boards beneath. A quotation for the works has been received and further quote(s) are being obtained by Crown Property Services. With the works estimated at £9.4k, this has been subject to a Section 20 Procedure. The works is scheduled to be carried out in December 2023, (with scaffolding) by TJ Smith Contracting Ltd and has been included in the 2023/4 budget. A copy of the Surveyor's Report can be seen by CLICKING HERE.