Rear Carpark Update

6 May 2025

Work on filling in the main tunnel with concrete has now been completed, the contractor having first removed the best part of 20 tonnes of rocks and soil which had fallen from the tunnel roof, having been loosened up by tree roots. The final concrete pour took place on Thursday, 17 April 2025. The scaffolding has since been removed followed by repair of the fencing and further clearing up of the site. The condition report for this phase of the works will be signed off by the Directors with Teignbridge District Council on Friday, 9 April 2025.

The main phase of the cliff works is expected to start in September 2025, when work will start on netting the cliff face, once the holiday season is over. In the meantime, some temporary safety fencing remains to stop cars being parked too close to the cliff face, as a precaution against any further rock falls.